This channel dredging will occur southeast of Gadsden Point, northwest of Apollo Beach and south of the Alafia River Channel.
FLORIDA-TAMPA BAY- HILLSBOROUGH BAY (CUTS A + C) AND ALAFIA RIVER: Dredging Operations.
Orion Marine Construction Inc will commence dredging operations in the Hillsborough Bay and the Alafia River on or about April 9 until approximately July 1, 2012.
Between Hillsborough Bay Lighted Buoys 10 to 31
Longitude: (Start) 27 48 13.7314 N, Latitude -82 27 52.5882 W
Longitude: (Middle) 27 48 42.4213 N, Latitude -82 26 53.5882 W
Longitude: (Stop) 27 53 53.0000 N, Latitude -82 26 21.3353 W
Alafia River
Longitude: (Start) 27 50 42.4068 N, Latitude -82 26 41.2325 W
Longitude: (End) 27 51 20.1865 N, Latitude -82 23 23.215 W
The project will involve the Hydraulic Cutter Suction Dredge `JERI-B’, Tenders: Gator and Jay-Jay. A mechanical clamshell Dredge `DRAVO’, Tenders: Miss Shirley and Erin P. The Dredge `JERI-B’ will operate 24/7, cell phone 904-412-8496. Floating rubber and submerged polyethylene pipeline associated with dredging operations will be utilized. Pipeline and vessels will be visibly lighted and marked according to Coast Guard regulations. Floating and submerged pipeline will be utilized from the dredge to the authorized dredged material discharge area. The pipeline path will be outside of and perpendicular to the navigation channel. Buoys with `Danger Submerged Pipeline’ will mark the submerged line as required by Coast Guard regulations. Mariners are urged to use extreme caution in the area, transit at their slowest safe speed to minimize wake, and proceed with caution after passing arrangements have been made. VHF ‘“ FM Channels Monitored: channels 12, 13, 16 and working channel 1. Project POC Mr. Jared Rackley, Project Manager cell (904) 868-9498.