Shoaling Reported at Hell Gate, AICW Statute Mile 602
The dredging of 2009 is slowly being overcome by shoaling through this perennial problem stretch, making Hell Gate another section that requires mid-to-high tide passage for vessels carrying 4ft or more draft. With his 6.25ft draft, Capt. Pascal is very alert to depth changes and his is the kind of vessel you would hope to be following through these trouble spots!
Definitely more shallow, by a couple of feet, again on the same lines I usually run thru there.
MM602, Hell Gate, 8′ to 9′ MLW thru most of the cut but some readings as low as 5′ to 6′ MLW around R90 and G89. Had 8′ of tides so I tried poking around for better readings, no luck. I usually pass about 40′ from R90, and about 30′ from G89; this time around it s definitely shallower by about 2 to 2.5′ compared to earlier this year.
Capt. Pascal Gademer
Click Here To View the Cruisers’ Net’s “AICW Problem Stretches” Listing For Hell Gate
Click Here To Open A Chart View Window, Zoomed To This AICW Problem Stretch