Updated 2027 Closure Schedule for W.P. Franklin and Ortona Locks for Major Maintenance, W P Franklin Lock, FL
The W P Franklin Lock is the westernmost lock on the Okeechobee Waterway. Our thanks to Specialist Jeffrey Prater for this notice.
Release No.: NR-26-053 Date: November 20, 2026
Contact: Jacksonville District Public Affairs Email: publicmail.cesaj-cc@usace.army.mil
FOR IMMEDIATE RELEASE
Jacksonville District announces revised maintenance closure schedule for
Ortona and W.P. Franklin locks
JACKSONVILLE, Fla.
– The U.S. Army Corps of Engineers (USACE), Jacksonville District, has revised the
scheduled maintenance closures for the Ortona and W.P. Franklin locks along the Okeechobee Waterway in response
to public feedback and to provide commercial and recreational vessel operators additional time to plan for potential
navigation impacts.
The revised schedule shifts the maintenance closures from the previously announced January start date to
March 2027. The anticipated duration of the closures remains unchanged.
The updated closure schedule is as follows:
• Ortona Lock: March 1 – April 30, 2027
• W.P. Franklin Lock: May 3 – June 30, 2027
The revised schedule reflects USACE’s commitment to considering stakeholder feedback while balancing the
need to complete essential maintenance on critical navigation infrastructure.
“We recognize the importance of the Okeechobee Waterway to the businesses, communities and recreational
boaters who depend on it,” said USACE Jacksonville District Commander Brandon Bowman. “We heard the concerns
raised about the original schedule and adjusted the maintenance windows to provide additional time for planning and
Page 1 of 2
US ARMY CORPS OF ENGINEERS | Jacksonville District
P.O. Box 4970 • Jacksonville, FL 32232-0019
Get Jacksonville District news and information at: www.saj.usace.army.mil or visit our social media sites:
Facebook – www.facebook.com/JacksonvilleDistrict | YouTube – www.youtube.com/JaxStrong | Twitter – www.twitter.com/JaxStrong | Flickr – www.flickr.com/photos/jaxstrongUS ARMY CORPS OF ENGINEERS | Jacksonville District BUILDING STRONG®
coordination. While these closures are necessary to maintain the long-term reliability of the locks, we remain
committed to communicating with those who may be affected.”
The maintenance activities will require temporary closures of each lock to navigation. These closures are
necessary to support maintenance and repairs that help ensure the continued safe and reliable operation of the
waterway’s navigation infrastructure.
USACE recognizes that the closures may affect commercial operations, marinas, recreational boating and
other waterway-dependent businesses. The district encourages vessel operators and affected stakeholders to review
the revised schedule and plan accordingly.
Jacksonville District will schedule additional stakeholder and community meetings to share information about
the planned maintenance activities, discuss anticipated navigation impacts and address questions from affected
businesses, vessel operators and the public.
Meeting dates, locations and participation details will be announced as they become available.
An updated Notice to Navigation reflecting the revised closure schedule will also be issued to provide official
notification to the marine community.
Jacksonville District will continue to provide updates as planning progresses and encourages waterway users
to monitor official USACE communications for the latest information.
-30-
Page 2 of 2
US ARMY CORPS OF ENGINEERS | Jacksonville District
P.O. Box 4970 • Jacksonville, FL 32232-0019
Get Jacksonville District news and information at: www.saj.usace.army.mil or visit our social media sites:
Facebook – www.bit.ly/JaxStrong_Facebook_Fan_Page | YouTube – www.youtube.com/JaxStrong | Twitter – www.twitter.com/JaxStrong | Flickr – www.flickr.com/photos/jaxstrong
Click Here To View the Okeechobee Waterway Cruisers Net Bridge Directory Listing For Franklin Lock
Click Here To Open A Chart View Window Zoomed To the Location of Franklin Lock



Be the first to comment!